Energy glossary
What it means
Your grid connection is the pipe between the public grid and your site. Its capacity is the most power that pipe can carry at once. On low voltage, the main breaker and cable set the limit. On medium voltage, you also agree an access capacity with the network operator: the power you reserve, in kVA. If kVA and kW are new to you, see kW vs kWh.
Think of the water main into a building. It does not matter how much water you use in a day; if everyone opens a tap at once, the pressure drops. Electricity works the same way, except that going over the limit trips a breaker or leads to extra costs.
Upgrading a connection takes time and money. In parts of Flanders, demand for new and bigger connections is rising fast, which can mean longer waits. See grid congestion.
An example
Example (hypothetical): an office building in Antwerp has a 250 kVA connection and a base load of 120 kW. The owner plans 40 charge points of 11 kW, or 440 kW if every car charges at full power at once. That would far exceed the connection. With load balancing, the chargers share the roughly 100 kW that is left, and most cars are still full by the end of the working day.
Why it matters for your company
Your connection is a fixed limit on growth. Using it well, by flattening peaks, is usually faster and cheaper than waiting for a bigger one, and it also lowers your capacity tariff in Flanders.
How BeLoaded helps
BeLoaded’s load balancing and company batteries keep your site within its connection, and our consulting services help you size what you need.