Energy glossary
What it means
The European grid runs at 50 Hz. When a power plant trips or demand jumps, the frequency drops. When there is too much power, it rises. FCR is the first line of defence.
Assets that provide FCR measure the frequency themselves and react automatically, in proportion to the deviation. For a deviation of 200 mHz, they must deliver half their power within 15 seconds and full power within 30 seconds. Elia does not need to send an order.
It works like the cruise control in a car: it corrects small speed changes instantly, before the driver has to step in. Here the driver is aFRR, followed by mFRR.
Elia buys all its FCR through the FCR Cooperation, a joint market of grid operators from nine countries, in daily auctions of 4-hour blocks.
An example
Example (hypothetical): a 1 MW battery is offered for FCR from 08:00 to 12:00. At 09:41 the frequency drops to 49.90 Hz, a deviation of 100 mHz. The battery automatically discharges 0.5 MW within seconds, then returns to rest as the frequency recovers.
Why it matters for your company
A battery is ideal for FCR: it reacts in milliseconds, and frequency moves up and down, so the energy needed is usually limited. FCR pays mainly for being available, so the battery earns while it mostly stands ready.