mFRR (manual Frequency Restoration Reserve)

manual Frequency Restoration Reserve · tertiary reserve · R3 · MARI · tertiaire reserve · tertiaire regeling · réserve tertiaire · réglage tertiaire

Energy glossary

mFRR (manual Frequency Restoration Reserve) is a balancing reserve that Elia activates on request for larger or longer imbalances, with full delivery within 12.5 minutes.

What it means

mFRR is the third line of defence. When an imbalance is large or lasts longer, for example after a power plant outage or a big error in the wind forecast, Elia asks providers to add power or use less. The provider must reach full delivery within 12.5 minutes and hold it as long as Elia asks. That frees the faster aFRR for the next event.

Think of a relay race: FCR and aFRR run the first laps, mFRR takes over for the long stretch.

Since May 2025, Elia is connected to MARI, the European platform where grid operators exchange mFRR energy. mFRR is open to more than batteries: industrial processes that can pause, or cooling that can wait, can take part too.

An example

Example (hypothetical): at 18:05 a large power plant trips and Elia activates mFRR. Within 12.5 minutes, a cold store cuts its consumption by 800 kW for 45 minutes and a battery discharges 1 MW. Both are paid for the energy they delivered.

Why it matters for your company

mFRR is activated less often than aFRR, but activations last longer. That makes it a good fit for flexible processes and larger batteries that can hold their power for a while. It is another way to earn from flexibility you already have, and to reduce the country’s imbalance.

How BeLoaded helps

BeLoaded offers your battery or flexible load to mFRR, aFRR and other markets through flexibility management, and picks the most valuable option at each moment.

Sources

  1. Elia – Elia Transmission Belgium gains access to MARI (press release, 23 May 2025)
  2. Elia – Activation for balancing

Updated: 29 October 2026

Frequently asked questions

What is the difference between aFRR and mFRR?

aFRR is steered automatically by a signal from Elia every few seconds and must deliver within 5 minutes. mFRR is activated by Elia on request, for larger or longer imbalances, and must deliver within 12.5 minutes. aFRR handles the constant small corrections, mFRR covers bigger events. Flexible industrial processes often fit mFRR better, while batteries can do both.

Can my company take part in mFRR without a battery?

Yes, if part of your consumption can be reduced on request for a while without hurting your operations. Think of cooling, pumps, compressors or heating processes. An aggregator measures your normal consumption, bundles your flexibility with other sites and bids it to Elia. Under Belgian rules, you can do this with a flexibility provider that is not your energy supplier.

Not sure where to start?

Answer four questions and get honest advice for your site, including when a battery is not the answer.