Balancing responsible party (BRP)

BRP · balance responsible party · access responsible party · ARP · evenwichtsverantwoordelijke · toegangsverantwoordelijke · responsable d'équilibre · responsable d'accès

Energy glossary

A balancing responsible party (BRP) is a company that must keep injection and offtake in its Belgian portfolio balanced every quarter-hour and settles any imbalance with Elia.

What it means

Every connection point on the Belgian grid must have a BRP. That can be a supplier, a producer, a trader or a large consumer. The BRP plans, for every quarter-hour, how much electricity its customers will take and inject, and buys or sells to match.

Think of the treasurer on a group trip: they keep the books balanced for everyone and settle any shortfall at the end.

Afterwards, Elia compares the plans with the meter data. If the BRP’s portfolio was out of balance, the BRP pays or receives the imbalance price for that gap. In Belgium, the BRP is also called the access responsible party.

An example

Example (hypothetical): a supplier is BRP for 5,000 business customers. It forecast 120 MWh for 09:00–09:15, but a cold morning pushed actual consumption to 124 MWh. The 4 MWh shortfall is settled at Elia’s imbalance price for that quarter-hour.

Why it matters for your company

Your supplier is almost always your BRP, and its imbalance costs end up in your price. When you start steering a battery or selling flexibility through an aggregator, you change what flows through your connection, and so the BRP’s balance. Belgian rules on Transfer of Energy settle this between the parties. That is why you can work with a flexibility provider other than your supplier.

How BeLoaded helps

BeLoaded arranges the aggregator and the pre-qualification for your flexibility through flexibility management. Questions about your contract set-up? Talk to our consulting team.

Sources

  1. Elia – The role of the BRP
  2. Elia – Transfer of Energy

Updated: 29 October 2026

Frequently asked questions

Is my company its own BRP?

Almost certainly not. For nearly all companies, the energy supplier acts as BRP. It makes the forecasts, sends the plans to Elia and settles the imbalance. Only large industrial users, producers and traders sign a BRP contract with Elia themselves. You can find out who your BRP is in your supply contract or by asking your supplier.

What is the difference between a BRP and a BSP?

A BRP keeps its own portfolio in balance and pays for its own imbalance. A balancing service provider (BSP) sells balancing services such as FCR, aFRR or mFRR to Elia, which uses them to correct the imbalance of the whole country. One company can play both roles, but they are separate contracts. An aggregator usually acts as BSP for the batteries and loads it bundles.